Phase 2 of the infrastructure improvement construction project will start Monday, April 28 and affect Regent Street from Bouchard Street to Walford Road, Bouchard Street from Regent Street to Southview Drive and Southview Drive from Bouchard Street to Cranbrook Crescent's east leg.

Construction will continue until September.

Final surface asphalt will be placed on Regent Street by July 2015.

Improvements include:
-Installation of trunk water main;
-Road reconstruction and widening with continuous centre turning lane and bicycle lanes;
-Storm and sanitary sewer improvements;
-New road granular, asphalt, curb and gutter, and sidewalk;
-Streetlight replacements;
-Installation of water main,
-Traffic signal improvements at Walford Road and Bouchard Street.

Safe access for pedestrians will be maintained.

Reader's Feedback

NorthernLife.ca may contain content submitted by readers, usually in the form of article comments. All reader comments and any opinions, advice, statements or other information contained in any messages posted or transmitted by any third party are the responsibility of the author of that message and not of NorthernLife.ca. The fact that a particular message is posted on or transmitted using this web site does not mean that NorthernLife.ca has endorsed that message in any way or verified the accuracy, completeness or usefulness of any message. We encourage visitors to NorthernLife.ca to report any objectionable content by using the "report abuse" link found in the comments section of this web site. Comment Guidelines