Curb removal and replacement will close the west bound curb lane on Brady Street, between Minto Street and the Brady Street underpass, starting Oct. 13.
Once work to the curb on the west side of the road is complete, removal and replacement will be done on the east bound side between the Brady Street underpass and Grey Street.
One lane of traffic will be maintained on the side the work is taking place. Work is expected to be completed by Oct. 16, weather permitting.
Sampling of monitoring wells will close the west bound inside lane at 391 Lorne Street, near Regent Street on Oct. 14. Work is expected between 9 a.m. and 3 p.m.
Sampling of monitoring wells will close the north bound curb lane on Notre Dame Avenue, at King Street, on Oct. 14. Work is expected between 9 a.m. to 3 p.m.